Suppose that a prospective contractor submits a proposal that falls under the threshold requiring certified cost or pricing data (currently $750,000) but subsequent to submitting the proposal, the Government decides to add additional quantities that causes the resultant contract to exceed that threshold. Is that contractor required to certify its cost or pricing data?